District heating

Suur-Savon Sähkö

Savosolar has been selected as general contractor to build the largest solar thermal system in Finland to date, on behalf of Suur-Savon Sähkö Oy for its district heating network in Puumala, which supplies households with healthy heating. In this hybrid installation the solar thermal system is producing both, high-temperature heat to district heating supply pipe and also low-temperature heat to improve heat pump plant COP.

Location

Finland

Construction status

Finished

Installation year

2021

Solution type

District heating

Number of collectors

27

Collector Area

431 m2
, gross

Collector Type

Savo 16 S

Power

300 kW

Energy production

175
MWh/a

Oulun Seudun Sähkö

Savosolar delivered -once again- the largest solar thermal installation in Finland. This system is located way North in Tupos, Liminka – less than 200 km from the Arctic Circle.

The heating load of Tupos district heating is usually covered by wood pellets. Yet during summer time, the load is often so low, that the substantial wood pellet burner cannot be properly used and an oil burner got used, instead. The special challenge here has been to design a very efficient solar thermal system that could replace the oil consumption in summer to run the district heating network almost completely fossil-free.

Palau-del-Vidre

In collaboration with Eiffage Energy Systèmes, Summa Energy is providing a solar thermal plant on trackers to supply heat to the greenhouses of Les Serres Vermeil, an organic vegetable grower located in Palau-del-Vidre, France.
Summa Energy with provide a turnkey solar thermal field of 396 Savo15S collectors, as well as all the engineering of the plant and the supervision software.

Fernwärme Ettenheim

As a general contractor, Savosolar built a solar thermal system on behalf of Fernwärme Ettenheim GmbH for the largest possible solar feed-in into the existing district heating network. 112 pieces Savo 15 SG-M large collectors generate fuel-free healthy heat, which is temporarily stored in two 100 m³ buffer storage tanks.
This also allows the operating hours of the CHP and the biomass boiler to be optimized. The scope of delivery included the fence and video surveillance system, as well as the creation of a meager meadow to enrich local biodiversity.

The construction work was temporarily interrupted due to the COVID19 restrictions. All system hydraulics were completely housed in a container. The keys were handed over in October 2020.

A PV system still to be built on the east side will generate the electricity for the pumps in the future.

The picture on the left shows the boiler house and the buffer storage tank. Handover of keys from Jari Varjotie, CEO Savosolar Oyj, to Peter Blaser, managing director of the customer.