District heating

Suur-Savon Sähkö

Savosolar has been selected as general contractor to build the largest solar thermal system in Finland to date, on behalf of Suur-Savon Sähkö Oy for its district heating network in Puumala, which supplies households with healthy heating. In this hybrid installation the solar thermal system is producing both, high-temperature heat to district heating supply pipe and also low-temperature heat to improve heat pump plant COP.

Location

Finland

Construction status

Finished

Installation year

2021

Solution type

District heating

Number of collectors

27

Collector Area

431 m2
, gross

Collector Type

Savo 16 S

Power

300 kW

Energy production

175
MWh/a

FORS A/S

FORS A/S is an energy company owned by three Danish municipalities. Their district heating plant in Jyderup has about 900 customers and produces about 5000 MWh solar thermal energy per year. For the rest of its energy production, the plant uses two gas boilers with 7 MW thermal capacity and two gas engines with 6 MW electrical capacity.

In Jyderup, the collector field is a so-called hybrid field, with both single and double glazed collectors. The single glazed collectors are in the cold end of the collector rows and increase the low temperature as rapidly as possible, while the double glazed collectors are located in the warm side of the collector rows where it is more important to reduce the heat losses. The collector field also has double stanchions which allows for two collector rows to connect to one and the same pipe and thereby save costs and thermal losses.

Lolland Forsyning

Lolland forsyning’s district heating plant in Søllested is located on the island of Lolland and was the first installation, where Savosolar’s double glazed collectors were used. The double glazing reduces heat losses through the glass side of collector and offers a higher efficiency, especially at higher operation temperature levels and during the darker months of the year. Søllested district heating plant has ca. 500 customers and also uses a 5 MW straw boiler and an oil burner to produce its heat.

The collector field in Søllested has a so-called hybrid field, with both single and double glazed collectors. The single glazed collectors are in the cold end of the collector rows and increase the low temperature as rapidly as possible, while the double glazed collectors are located in the warm side of the collector rows where it is more important to reduce the heat losses.

In Søllested, Savosolar was faced with a special challenge since the customer’s land has a sewerage pipe running through it. Since the owner of the sewer pipe needs to be able to access it in case of maintenance, Savosolar supplied a collector field which both optimised the use of the available land, while still providing access to the sewer pipe

Narbonne

With this new solar thermal plant for newHeat, Savosolar add a new leading reference in the French market of solar district heating. This approximately 3,000 m2 solar thermal field (aperture), will allow to replace 2,410 MWh of former gas heated heat by renewable heat on Narbonne’s city network, manage by a subsidary of Dalkia.

Savosolar, on the behalf of newHeat, built mainly the whole solar plant, from the solar collector’s field until the outlet of the heat exchanger to the storage thermal tank, ie: solar field, piping and solar station. More then 200 of our Savo 15 SG-M collectors, ensuring a high energy yield while reducing 510 tons of CO2 emissions per year from the district heating system of the city. The production of solar field during winter will even allow an increasing of the yield of the existing biomass boiler.