Savosolar was happy to sign its so far largest delivery contract with Grenaa Varmeværk in 2018. Savosolar’s highly efficient Savo 15 premium collectors are installed right next to an existing solar collector field which had been commissioned in 2014.
In this turn-key project Savosolar acts as the main contractor enlarging the solar fraction of the district heating network. Its operator, Grenaa Varmeværk, is producing about 146,000 MWh of heat per year. By using solar thermal it has managed to keep their customers´ heat price among the lowest in the whole of Denmark.
The new solar field with Savosolar collectors will increase the overall solar yield and ensure lowest energy production costs also in the future.
Løgumkloster Fjernvarme is a district heating company which annually supplies 35,000 MWh of heat to over 1,500 customers. Heat is produced with a hybrid heating system consisting of a 3 MW pellet boiler, a 1.3 MW hybrid heatpump, a 3 MW absorption heat pump and a solar collector field of 15,300 m2. Additionally, the plant has two gas engines which are capable of producing 7.6 MW of heat and 6 MW of electricity and a 10 MW gas boiler which acts as back-up.
In 2015, Savosolar delivered a 9,700 m2 solar thermal field to Løgumkloster. The second order of 5,600 m2 was delivered and commissioned in the beginning of 2016. The complete field consists of 1030 Savo 15 SG collectors and covers about 20% of the annual thermal energy need of the district heating network. The largest part of the heat demand is covered by the pellet boiler, but Løgumkloster Fjernvarme has plans to change this in the future by extending the solar field and building a large seasonal water storage.
As a general contractor, Savosolar built a solar thermal system on behalf of Fernwärme Ettenheim GmbH for the largest possible solar feed-in into the existing district heating network. 112 pieces Savo 15 SG-M large collectors generate fuel-free healthy heat, which is temporarily stored in two 100 m³ buffer storage tanks.
This also allows the operating hours of the CHP and the biomass boiler to be optimized. The scope of delivery included the fence and video surveillance system, as well as the creation of a meager meadow to enrich local biodiversity.
The construction work was temporarily interrupted due to the COVID19 restrictions. All system hydraulics were completely housed in a container. The keys were handed over in October 2020.
A PV system still to be built on the east side will generate the electricity for the pumps in the future.
The picture on the left shows the boiler house and the buffer storage tank. Handover of keys from Jari Varjotie, CEO Savosolar Oyj, to Peter Blaser, managing director of the customer.
Savosolar delivered -once again- the largest solar thermal installation in Finland. This system is located way North in Tupos, Liminka – less than 200 km from the Arctic Circle.
The heating load of Tupos district heating is usually covered by wood pellets. Yet during summer time, the load is often so low, that the substantial wood pellet burner cannot be properly used and an oil burner got used, instead. The special challenge here has been to design a very efficient solar thermal system that could replace the oil consumption in summer to run the district heating network almost completely fossil-free.