Industrial process heating

La Caridad

Savosolar and its partner Jorgensen have been selected by Grupo Mexico for the implementation of their first solar thermal plant to deliver carbon free heat to their mining process. In this very energy efficient mining process, only 62 pieces of Savo 15SGM large scale high performance flat plate collectors are sufficient deliver 1,2 GWh of energy over the year and cover 100% of the production need during most of the sunny season.

Location

Mexico

Construction status

Finished

Installation year

2023

Solution type

Industrial process heating

Number of collectors

62

Collector Area

990 m2
, gross

Collector Type

Savo 15SG M

Power

700 kW

Energy production

1200
MWh/a

Etelä-Savon Energia

Mikkeli city, the home of Savosolar received the “Inspiring Solution Award” in 2018 Celsius City Summit for the Ristiina Village project. It is a green district heating energy concept with a clever combination of solar thermal and wood chips.

Savosolar was involved in this award winning project by delivering turn-key solar district heating installation to the Ristiina district heating plant.

Suur-Savon Sähkö

Savosolar has been selected as general contractor to build the largest solar thermal system in Finland to date, on behalf of Suur-Savon Sähkö Oy for its district heating network in Puumala, which supplies households with healthy heating. In this hybrid installation the solar thermal system is producing both, high-temperature heat to district heating supply pipe and also low-temperature heat to improve heat pump plant COP.

Lolland Forsyning

Lolland forsyning’s district heating plant in Søllested is located on the island of Lolland and was the first installation, where Savosolar’s double glazed collectors were used. The double glazing reduces heat losses through the glass side of collector and offers a higher efficiency, especially at higher operation temperature levels and during the darker months of the year. Søllested district heating plant has ca. 500 customers and also uses a 5 MW straw boiler and an oil burner to produce its heat.

The collector field in Søllested has a so-called hybrid field, with both single and double glazed collectors. The single glazed collectors are in the cold end of the collector rows and increase the low temperature as rapidly as possible, while the double glazed collectors are located in the warm side of the collector rows where it is more important to reduce the heat losses.

In Søllested, Savosolar was faced with a special challenge since the customer’s land has a sewerage pipe running through it. Since the owner of the sewer pipe needs to be able to access it in case of maintenance, Savosolar supplied a collector field which both optimised the use of the available land, while still providing access to the sewer pipe